Ford GE-2 Glendale, KY
Description
Hodess is supporting a 1,220,040 SF lithium-ion battery manufacturing facility delivered under a cost-plus model, encompassing over 20 football fields of ISO Class 7 and ISO Class 8 clean and dry space. The project includes the accelerated “Mission-X” initiative, advancing equipment start-up to February 2024 from the originally scheduled June 2024 milestone.
To meet this compressed timeline, Hodess has implemented continuous cleaning operations, furnished and installed overhead doors to create temporary airlocks, and maintained full-time design support to provide expedited responses. The team also accelerated air shower procurement and installation while scaling staffing to support multiple shifts and increased production demands.
Industry
Battery
Project Delivery
Cost-Plus
ISO Class
ISO 7